success stories

Coperion’s pneumatic conveying technologies enable blue chip coffee roaster to deliver on increased demand

Coffee roaster benefits from adopting new conveying technologies

The coffee industry is constantly growing and competitively producing new flavors of coffee and coffee derived products. These trends present producers with many process challenges such as quality, finish and of course taste.

A leading multinational chain of coffee houses and roastery reserves approached Coperion to discuss problems they were facing when conveying their green and roasted coffee beans to a new roaster. The existing roasting room was heavily congested and needed to be ‘up-graded’ to meet growing coffee demands seen in both the UK and Europe.

The client outlined special requirements for the storage of green beans, as well as for the conveying of roasted coffee. The entire system involving Coperion E-finity & EDIP pneumatic conveying technologies would need to ensure limited product breakage and reduced power consumption to enable the client to meet its sustainability goals. Coperion’s in depth knowledge of the client meant that they could utilize their experience and technical know-how gained from previous contracts to assure them that they were ideally placed to improve and optimize both the client’s existing and new processes quickly, using 3D scanning & modelling tools.

Coffee roaster delivered on increased demand

Technological advances alleviate strict time constraints

The customer was under strict time constraints due to the pressure on their already congested system. To alleviate these problems, Coperion utilized the latest 3D scanning and modelling techniques, working with the client’s main contractor to achieve success.

The ability to use remote technology to lessen the impact for the client and ensure the project progressed in accordance with their timeframes was fundamental to its success. Effectively utilizing 3D scanning techniques meant that Coperion were able to deliver precise site layouts and equipment stack-ups without the need to visit site. The optimized modelling contributed to each conveying line being established with the smoothest route possible to keep breakage to a minimum. Coperion employed their extensive test data and project references to allow ‘smart‘ decisions to be made regarding conveying technologies. This, combined with strong project team integration from day 1, provided advance visibility of any design issues so that these could be rectified prior to manufacture and site assembly.

Pioneering solutions to complex conveying needs

The client detailed a number of specific requests they had around the delivery of their green beans and roasted coffee conveying needs; to meet the demand to the new storage and packing lines.

For roasted coffee beans a breakage guarantee was required. Coperion utilized their leading-edge E-Finity low pressure continuous dense phase technology to achieve the required process guarantee which was less than 1.0% by weight fines generation per transfer.

Coperion recommended their EDIP technology as it is designed to optimize conveying parameters to reduce energy consumption and deliver the required increase of green beans to storage. Typical energy savings range from 20-40% verse operating the same system at full blower speed. The installation of the EDIP system resulted in a dilute phase system that dramatically reduced power consumption, bean damage and system wear compared to other contemporary dilute phase systems.

Coperion also recommended the E-Finity low pressure, continuous dense phase conveying system, to transfer the coffee beans, as it is especially designed for fragile materials. With precise pressure monitoring to allow the system to operate efficiently under all conditions, while gently inducing materials through the convey line in slug form, it was perfect for the customer’s specific needs and was able to meet the performance criteria.

The recommendations Coperion proposed delivered the following benefits for the customer:

  • Reduced product degradation for all roasted coffee
  • Minimized velocity in all systems
  • Reduced energy consumption by up to 30%
  • Reduced wear on equipment  
  • Increase conveying capacity for next phase of the project
  • Decreased project CAPEX cost by changing from compressed air to blower technology (E-finity and EDIP)

With excellent cross-regional communication and a strong ongoing customer relationship, product modifications were designed and developed explicitly for the customer’s requirements. This meant that the new systems installed not only met their immediate needs, but the Coperion team’s forward-thinking approach ensured future conveying throughput would also be met. Coperion were able to progress the project to completion, delivering it on time, on budget and to the customer’s satisfaction. The client stated that ‘working with Coperion on this major project has been an absolute joy.’

Related solutions

Image forOther food

Other food

Image forDesign & engineering

Design & engineering

Image forConveying

Conveying

Image forProject management & execution

Project management & execution

Stay connected

Subscribe to keep up to date with current perspectives, events, white papers and more.